Present Status of the project

Time based work plan and achievement Upto February, 2017

Project Name : Padma Multipurpose Bridge Project.
Ministry/Division/Agency: Ministry of Road Transport and Bridges, Bridges Division, Bangladesh Bridge Authority
Project Progress : 40.50%

Work Description as per work plan (major work)

Work start date according to work plan: November 2014
Work end date according to work plan: November 2018
Status:
Main Bridge’s 25 nos. pile has been driven out up to bottom 70m and 19 nos. piles have been driven out up to 128m. 20,000m steel plate fabrication of Main Bridge’s has been done (out of 30,000m). 1,25,000 Ton steel plate out of 1,29,000 Ton has already been in site for pile driving work. Super structure of 3D assembling work is ongoing in both China and Bangladesh. 04nos. Trusses (150m span) fabrication work is being continued at Mawa Construction Yard. Already all 08 Nos. Test Pile of Main Bridge has been done out of 08 Nos and additional test piling of viaduct is ongoing. The work of 150 m wide channel along alignment of Main Bridge is being continued. At Janjira site 56nos. of Board piling work of Viaduct has been done and construction of pile cap is ongoing. Transition pier’s 4 nos. Bored pile with 3m dia has been done and load testing of service pile is going on.
Percent Completed: 35.50%

Work start date according to work plan: November 2014
Work end date according to work plan: November 2018
Status:
Mobilization of equipmentsuch as various sizes rock, stone chips, Sylhet sand, cement and other construction materials is going on.Casting of 33,00,000 Nos. concrete blocks out of 1,33,01,248 Nos. has been completed.Dumping of 21,12,000 nos. Geo-bags out of 2,12,75,000 Nos. has been completed. At Janjira side chainage 5+300m to chainage 7+000m of permanent dredging workis ongoing& at Mawa side 800kg Geo bag dumping has been done over 1100m apron moreover filling is completed to the two voids around 7,00,000m3created during in rainy season.
Percent Completed: 29.00%

Work start date according to work plan: November 2014
Work end date according to work plan: November 2019
Status:Supervision of work is going on.
Percent Completed: 41%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2016
Status: Approach Road = 10.579 km, Service Road =9.589 km, and Connecting Road =4.495 kmconstruction work is ongoing. Construction work of 5 nos Bridge, 20 nos Culvert, 8 nos Underpass as well as Toll Plaza, Police Station & Fire Station is also being continued.
Percent Completed: 91%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2018 (including 1 year defect liability period)
Status: Supervision of work is going on.
Percent Completed: 80%

Work start date according to work plan: August 2006
Work end date according to work plan: June 2015
Status:
   a) Munshigonj: Proposed land =400.84 hectares; Acquisition land = 331.25 hectares; Possession taken by PMBP = 262.10 hectares.
   b) Madaripur: Proposed land = 1213.81 hectares; Acquisition land = 549.85 hectares; Possession taken by PMBP =549.76 hectares
   c) Shariatpur: Proposed land = 740.84 hectares; Acquisition land = 591.56 hectares; Possession taken by PMBP = 502.99 hectares

# Total proposed land for 03 Districts =2355.49 hectares;
# Total acquisition land for 03 Districts =1472.66 hectares;
# Total Possession of land taken by PMBP in 03 Districts =1314.85 hectares.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2020
Status:
   a) Tk. 603.17 crore additional grants have been handed over to the PAP up to February 2017.
   b) 2103 Nos. plots have been handed over out of 2298 Nos. to the PAP which is recommended by the “Project Level Plot Allocation Committee” up to February 2017. Among them it has been handed over 608 Nos. Landless families without any cost. Moreover house development facility has been provided to the 143 nos. effected people.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2020
Status:
   a) Tree plantation has been started from 2012 and 87,457 Nos. of tree plantation has been completed up to February 2017 in resettlement area, approach road and service area on both side of the river.
   b) Consulting firm Agriconsulting S.P.A & SODEV Consult International Ltd.are continuing their work on for "Biodiversity Baseline Survey and Preparing Monitoring Plan, Identifying Location of the protected Sanctuary and Developing a Sanctuary Plan of PMBP"
   c) MoU has been signed with Zoological Department of Dhaka University to stablish a Museum in the project area. For this purpose, proposed signing of contract agreement has been completed. And 955 nos. sample of species has been collected and preserved till February 2017.
   d) For "Consultancy Services for Preparing a Comprehensive Documentation of Padma Multipurpose Bridge Project," negotiation has been signed between Impress telefilm and PMBP on 17/02/2016. "Commencement of service" has been provided to this institution for doing work. Work is ongoing.

Status:
Final Inception Report and Quality Assurance Manual submitted by Management Support Consultant (MSC) Service Contract of Padma Multipurpose Bridge Project. Work is ongoing.

Download time based work plan and project progress (fast track):  microsoft word logo