Present Status of the project

Time based work plan and achievement Upto September, 2017

Project Name : Padma Multipurpose Bridge Project.
Ministry/Division/Agency: Ministry of Road Transport and Bridges, Bridges Division, Bangladesh Bridge Authority
Project Progress : 48.00%

Work Description as per work plan (major work)

Work start date according to work plan: November 2014
Work end date according to work plan: November 2018
Status:
River Span of Main Bridge’s total Pier 40 Nos., Total Steel Pile 240 Nos., 90 Completed Bottom Section Driving, 63 Completed Top Section Driving, 24 Completed Bottom Concrete Plug, 24 Completed Base Grouting, 24 Completed Pile, 2 Completed Pier Column and P1 & P42 Total Pier 2 Nos., Total Bored Concrete pile 28 Nos., 16 Completed Base Groutiting, 16 Completed Pile. Janjira Viaduct Total Pier 40 Nos., Total Bored Concrete Pile 193 Nos., 154 Completed Base Grouting, 193 Completed Pile, 2 Completed Pier Column and Mawa Viaduct Total Pier 37 Nos., Total Bored Concrete Pile 172 Nos. 23 Completed Pile, Truss Fabrication: Total Number of Truss span 41, 11 Reached Span Number at Construction Site, 7 Fabricated Span Number at Construction Site, 1 Span Erection on Pier P37 & P38 and Fabrication Work is ongoing for the rest of three.Construction of Steel member from using steel plate at Workshop in China= 12 Nos (Staying at Mawa ghat for Shipment) and another 7 nos. construction work is on going.
Percent Completed: 51.00%

Work start date according to work plan: November 2014
Work end date according to work plan: November 2018
Status:
Mobilization of equipment such as various sizes rock, stone chips, Sylhet sand, cement and other construction materials is going on. Casting of 30,26,555 Nos. concrete blocks out of 1,33,01,248 Nos. has been completed. Dumping of 26,79,619 nos. Geo-bags out of 2,12,75,000 Nos. has been completed. At Mawa site out of 1.8 km river training work from chainage -500m to +900m (1.4 km) 800kg Geo-bag damping has been completed at 5 layer in lunching apron and in trial section at Jajira site from chainage -500m to +140m (680m) 125 kg Geo-bag damping work has been completed successfully. Besides at Mawa site Scour Holes (Void 1 & Void 2) at slope were filled and 125 kg Geo-bag damping work has been completed above them. Moreover 8 nos pond filling work have been completed at embankment zone. At Jajira site trial section from chainage -980m to -400m (580m) 800kg geo bag damping have been completed at 5 layers. Besides 125kg geo bag damping have been completed at 3 layers and in the mean while above those rock damping work has been completed upto 44,910 cubic meters and CC block damping has been completed upto 11,13,354 nos. Rock dumping upgradation work is ongoing now. Besides at Jajira site embankment work from 1+650m to 2+700m is ongoing. Slope Trimming at the countryside of the embankment in being continued and sandy loam placement is also ongoing. At Janjira site from chainage 4+900m to 6+500m (1.2 km) bulk dredging has been completed and from chainage 0+100m to 1+100m bulk dredging is ongoing. Final Trimming work is ongoing from chainage 4+900m to 6+500m. In the meantime, casting of 93,49,887 nos CC half bricks out of 5,34,50,500 nos has been completed and the rest of work is ongoing. Besides 14,54,800 nos CC half Bricks dumping was completed. At Mawa site from chainage 100m to 800m embankment work is ongoing.
Percent Completed: 34.20%

Work start date according to work plan: November 2014
Work end date according to work plan: November 2019
Status:Supervision of work is going on.
Percent Completed: 55%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2016
Status: Approach Road = 10.637 km, Service Road =9.589 km, link road=5.495km and Connecting Road =4.495 km construction work is ongoing. Construction work of 5 nos Bridge, 20 nos Culvert, 8 nos Underpass as well as Toll Plaza, Police Station & Fire Station is also being continued.
Percent Completed: 99.50%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: January 2014
Work end date according to work plan: July 2017
Status: Work is substantially complete.
Percent Completed: 100%

Work start date according to work plan: October 2013
Work end date according to work plan: October 2018 (including 1 year defect liability period)
Status: Supervision of work is going on.
Percent Completed: 92%

Work start date according to work plan: August 2006
Work end date according to work plan: June 2015
Status:
   a) a) Munshigonj:Proposed land =412.70 hectares; Acquisition land = 331.25 hectares; Possession taken by PMBP = 319.91 hectares.
   b) Madaripur: Proposed land = 1213.81 hectares; Acquisition land = 549.85 hectares; Possession taken by PMBP =549.85 hectares
   c) c) Shariatpur: Proposed land = 741.46 hectares; Acquisition land = 591.56 hectares; Possession taken by PMBP = 579.74 hectares


# Total proposed land for 03 districts =2367.97 hectares;
# Total acquisition land for 03 Districts =1472.66 hectares;
# Total Possession of land taken by PMBP in 3 districts =1449.41 hectares.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2020
Status:
   a) Tk. 621.13 crore additional grants have been handed over to the PAP up to October/2017.

   b) 2441 Nos. plots have been handed over to the PAP which is recommended by the 'Project Level Plot Allocation Committee' up to October/2017. Among them it has been handed over 628 Nos. of plots to Landless families without any cost. Moreover house development facility has been provided to the 475 nos. affected people.

Work start date according to work plan: June 2009
Work end date according to work plan: June 2020
Status:
   a) 1,51,457 Nos. of tree plantation has been completed up to October/2017 in resettlement area, approach road and service area on both side of the river. The maintenance work of the planted trees has been completed in June/2017. Preparation for plantation in approach road is ongoing.
   b) MoU has been signed with Zoological Department of Dhaka University to stablish a Museum in the project area. For this purpose, proposed signing of contract agreement has been completed. And 1249 nos. sample of species has been collected and preserved till October/2017.
   c) For 'Consultancy Services for Preparing a Comprehensive Documentation of Padma Multipurpose Bridge Project,' negotiation has been signed between Impress telefilm and PMBP on 17/02/2016. According to contact the 1hr video recorded for the first 6 (six) month was received. Monthly progress report is being send regularly.

Status:
Final Inception Report and Quality Assurance Manual submitted by Management Support Consultant (MSC) Service Contract of Padma Multipurpose Bridge Project. Work is ongoing. Percent Completed: 37%

Download time based work plan and fast track project progress October 2017 (Bangla version) :  microsoft word logo

Download time based work plan and fast track project progress October 2017 (English version) :  microsoft word logo